"We've got a tractor pulling and a tractor pushing because the magnitude of the load would be too great for one tractor to pull and take care of on its own," Lucien Richard told WMTW as the first convoy made its way south from Jay at the end of September. Richard is site manager for JGT2 Redevelopment, the company that owns the former mill site in Jay.
The load behind those two tractors was a heat recovery steam generator from the former Pixelle/International Paper mill. It was just over 219 feet long, 20 feet wide and 19.5 feet high, with a gross weight of 683,530 pounds. It traveled about 90 miles, and its last few miles ran through South Portland on Route 1, Broadway and Elm Street.
The convoys don't continue past South Portland. The city is where the road part of the trip ends, because the harbor at the end of Elm Street is how these generators leave Maine. There are nine generators in all. On the schedule the city has posted, three more are due to cross Broadway between now and December 8.
Nine generators, one way out of Jay
Barnhart Crane & Rigging is running the move. Its job is to carry the steam generators from the closed mill in Jay to Turner Island on Elm Street in South Portland. On September 30, WMTW reported that the first transport was already running behind its original timeline. The station also noted that the load and its support team would take up most or all of the road in several places.
The route explains why each trip takes several nights. Here is how WMTW laid it out: Route 4, Route 117, Route 26, Route 202, Route 22, Route 1, then Broadway to Elm Street along the waterfront. It passes through Turner, Buckfield, Paris, Norway, Oxford, Poland, Gray, Windham and Scarborough, and it climbs over Streaked Mountain. On the first trip, Route 117 closed from Weston Road to East Hebron Road from about 6 p.m. until midnight while the convoy went by.
WGME reported on October 6 that the first load had reached Turner Island, where it was expected to be put on a boat and shipped south. The next day, WMTW confirmed that the first delivery was finished and that the project covers nine loads in total.
Why the route ends at the end of Elm Street
WMTW described the destination as the end of Elm Street in South Portland, near the oil tanks. All nine generators are to gather there, be hoisted onto barges, and go to paper mills in Alabama, Virginia and Louisiana.
In Oxford, Gray and Buxton, a generator spends a night or a weekend staged between legs and then moves on. In South Portland it gets off the road for good. At Turner Island, the 90-mile overland haul becomes a water route to three states.
Inside the city, every load follows the same path:
- Route 1 into South Portland
- Broadway
- Elm Street
- The waterfront site at Turner Island
The city has published Barnhart's public notice, which says the work is coordinated with MaineDOT, Maine State Police, local law enforcement, utility companies and other project stakeholders. It also says the remaining moves will happen mostly overnight to keep the impact on daytime traffic low.
The weekly rhythm, and what's left of it
The posted schedule turned the project into a repeating pattern of four legs. Each load leaves Jay in the evening and moves to Oxford. It goes on from Oxford to Gray, usually after a weekend staged in Oxford, then from Gray to Buxton the next night, and from Buxton to South Portland the night after that. That last leg starts at 9 p.m. According to that schedule, six of the nine generators were due at Turner Island by the night of November 10.
From today, Thursday, November 12, three loads remain. Load 7 is scheduled to leave Jay this evening.
| Load | Leaves Jay | Oxford to Gray | Gray to Buxton | Buxton to South Portland |
|---|---|---|---|---|
| Load 7 | Thu., Nov. 12, 6 p.m. | Sun., Nov. 15, 7 p.m. | Mon., Nov. 16, 9 p.m. | Tue., Nov. 17, 9 p.m. |
| Load 8 | Sun., Nov. 29, 6 p.m. | Mon., Nov. 30, 7 p.m. | Tue., Dec. 1, 9 p.m. | Wed., Dec. 2, 9 p.m. |
| Load 9 | Thu., Dec. 3, 6 p.m. | Sun., Dec. 6, 7 p.m. | Mon., Dec. 7, 9 p.m. | Tue., Dec. 8, 9 p.m. |
There's a gap in the middle. The notice says no oversized loads are currently planned for Thanksgiving week, and work is expected to resume after the holiday. The pause also tightens Load 8. It runs four nights in a row, Sunday through Wednesday, compared with the Thursday-to-Tuesday spacing of the other loads. That puts its South Portland night on a Wednesday, the only one of the three that isn't a Tuesday.
The notice says every date, time and road-closure plan is tentative. Weather, safety requirements, permitting, equipment availability or other operational needs could change them, and updated notices will be issued as needed. Treat the table as the plan as posted, not as a set of fixed appointments.
What the last few miles look like overnight
The posted notice gives only one detailed estimate for the South Portland leg, for Load 2 in mid-October. That load was set to leave Buxton at 9 p.m. on Tuesday, October 13. It was expected to reach South Portland between 1 and 2 a.m. and to arrive at its final destination at 5 a.m. on Wednesday, October 14.
That estimate shows where the night goes. The trip from Buxton to the city line was planned at four to five hours. The stretch from the city line to the site at the end of Elm Street was given roughly three to four hours more. Moving a 219-foot load through Route 1, Broadway and Elm Street was expected to take almost as long as everything before it. Later loads list only the 9 p.m. start, but they use the same route and the same overnight window.
Each Buxton-to-South Portland night also lists a jumper bridge closure starting at 10 p.m. A jumper bridge is a temporary span the crews put in place along the route. The travel advisory tells motorists to expect:
- Overnight oversized load movements
- Temporary road closures while jumper bridges are installed
- Signed detours during closures
- Rolling traffic delays along the route
- Utility work and support vehicles in the corridor
- Police-assisted traffic control at key intersections and crossings
The notice asks drivers to allow extra time, follow posted detours, obey traffic control devices, and follow directions from law enforcement and transportation crews. The 9 p.m. start and the 1-to-5 a.m. window from Load 2 suggest the Broadway and Elm Street portion falls in the early-morning hours. Late-shift commutes, early flights and overnight errands along that corridor on November 17, December 2 and December 8 are the trips most likely to run into it.
After December 8
If Load 9 keeps its date, it will be the ninth and last generator to arrive at Turner Island. From there, the remaining step is the one WMTW described from the beginning. The generators are to be lifted onto barges and taken to paper mills in Alabama, Virginia and Louisiana.
The equipment is moving from one mill town in western Maine to mills in three southern states. South Portland is the stop where it changes from trucks to water, and the city's posted notice will carry any schedule changes before the last of it rolls down Broadway.
South Portland's working harbor is part of daily life for the people who live near it, and we pay attention to those details when we talk with owners in the neighborhoods off Broadway and along the Elm Street waterfront. If you're thinking about what your South Portland home could bring in this market, Linda MacDonald and our team would be glad to prepare a complimentary home valuation.